Home / Tools / Grants and paperwork / Do solar panels need planning permission?

Do solar panels need planning permission?

Most rooftop solar in England is permitted development under GPDO Part 14 Class A as rewritten in August 2026: the checks that matter. For the UK these pages use the checked rules, with source and date on the page. For other countries the tool uses only values you enter: always check the current official terms.

Your figures and assumptions

Yields checked in PVGIS SARAH3 for 18 UK towns and cities: from 853 kWh/kWp in Glasgow to 1,122 kWh/kWp in Plymouth, at 5 kWp, south-facing, 35 degree tilt.
5 kWp
Your household's use over a year, from your bills or meter.
35 °
0 kWh
Prices and costs (sourced, all editable)
Automatic uses the DESNZ median install cost, MCS-certified installations, April 2025 to March 2026: £1,780 per kW for systems up to 4 kW, £1,697 per kW above 4 kW up to 10 kW, £1,262 per kW above that. It switches band with the system size you set. Installed prices include 0% VAT on installation until 31 March 2027, then 5%.
Type the rate from your own quotes if you prefer it to the DESNZ median.
Starting value: Ofgem price cap, 1 October to 31 December 2026, Direct Debit, GB average, including VAT: 26.32p per kWh. Replace it with the rate on your own bill.
Starting value: Ofgem price cap, same period, 54.83p per day. The standing charge is added to the bill whether or not you have solar: 365 days at 54.83p is £200.13 a year.
This field starts empty on purpose: there is no default SEG rate. SEG rates are set by suppliers, not by the government, and the only floor is above 0p per kWh. Enter the rate on your own supplier's SEG tariff. As a guide to what has been offered, Ofgem's Year 5 annual report put the average offered rate at 10.8p per kWh (April 2024 to March 2025, published December 2025): a dated market statistic, not a rate you will get. Leave the field empty and exports are valued at £0.

Every figure can be changed. For a result fitted to your home, use your own tariff and your own quotes.

Editable estimate, used when a battery is included.
Coverage: 18 UK towns and cities, each with a checked PVGIS yield.
Planning position for this system
Usually permitted development in England
Live result
Annual generation
5,094 kWh
Generation per kWp
1,019 kWh/kWp
Used in the home
1,783 kWh
Exported
3,311 kWh
SEG rate entered
none
Annual benefit
£469

Preparation list, not legal advice: most rooftop solar on a house in England is permitted development under GPDO Part 14 Class A, as rewritten by SI 2026 No. 896 with effect from 27 August 2026. Listed buildings and conservation areas need extra care, and an Article 4 direction can remove permitted development rights locally. Scotland, Wales and Northern Ireland have their own rules, which differ: check your nation's guidance and your local planning authority. Sources: GPDO 2015 Part 14 Class A; SI 2026 No. 896. Checked 8 November 2026.

Worked example

The same calculation with example values: Plymouth, tilt 30 degrees, other values as in the form.

Planning position for this system
Usually permitted development in England
Live result
Annual generation
5,593 kWh
Generation per kWp
1,119 kWh/kWp
Used in the home
1,958 kWh
Exported
3,636 kWh

How the calculation works

The Smart Export Guarantee (SEG Order 2019) pays for metered exports through a supplier's SEG tariff. Rates are set by suppliers, not by the government; the only floor is above 0p per kWh. You normally need an MCS certificate (or equivalent), a meter capable of half-hourly readings and an export MPAN. SEG is Great Britain only: Northern Ireland is outside it. Ofgem's Year 5 annual report put the average offered rate at 10.8p per kWh (April 2024 to March 2025): a dated statistic, never a promised rate, and this site uses no default SEG rate.

Grants and paperwork: there is no general grant for households who can pay. ECO4 (Great Britain, low-income and vulnerable households) is funded to 31 December 2026. The Warm Homes: Local Grant (England only, EPC D to G, household income usually £36,000 or less, solar a listed measure) runs to 31 March 2028. VAT on installation is 0% until 31 March 2027, then 5%. Most rooftop solar in England is permitted development under GPDO Part 14 Class A as rewritten by SI 2026 No. 896 (in force 27 August 2026); listed buildings and conservation areas need extra care, and Scotland, Wales and Northern Ireland have their own rules. Grid connection: G98 up to 3.68 kW per phase (connect, then notify the DNO within 28 days); G99 needs DNO approval before connecting above that.

Common questions

Is there a grant for solar panels?

Not a general one. ECO4 supports low-income and vulnerable households in Great Britain and is funded to 31 December 2026. The Warm Homes: Local Grant covers England only, homes rated EPC D to G with household income usually £36,000 or less, to 31 March 2028. Solar Together is group buying, not a grant. Everyone qualifying gets the 0% VAT relief on installation (to 31 March 2027) and SEG payments for exports.

Do solar panels need planning permission?

Most rooftop solar on a house in England is permitted development under GPDO Part 14 Class A, as rewritten by SI 2026 No. 896 from 27 August 2026. Listed buildings and conservation areas need extra care. Scotland, Wales and Northern Ireland have their own rules: check your nation's guidance.

What are G98 and G99?

The grid connection routes in Great Britain. Up to 3.68 kW per phase, G98 means connect and then notify your distribution network operator within 28 days. Above that, G99 means you need the DNO's approval before you connect.